Linda and Chuck Schneider are both retired teachers and challenged with regular daily living since Chuck suffered a stroke. The scope of this project may include a small addition to the home providing an accessible bathroom and safe access to the outdoors.

Schneider Project Fundraising Flyer

Chuck and Linda Schneider



Project Updates

February 2016

  • After exploratory digging, it was discovered that structural plan needs to be updated.
  • Clearing and grubbing complete.
  • Batter board layout and excavation complete. Excavation to possibly be filled based upon setback findings.
  • Currently looking for abatement, concrete, rebar, lumber, and geotechnical surveyor.
  • Geotechnical survey complete. Foundation to remain a footing system.
  • Backfill of geotechnical survey excavation complete.
  • Waiting on project redesign.

March 2016

  • Footers dug. Team to pour footers 03.12.16
  • Project redesign released
  • Group to begin procurement process. Piping and backfill have been donated.
  • Permit to be submitted this week.
  • Installed Formwork for stem walls
  • Poured Footers/Stem wall
  • Backfilled and compacted excavation
  • Underground sanitary rough installed
  • Underground inspection complete 4/1
  • Poured Slab
  • Prefabricated Walls in IS Lab