Max is an 8-year-old boy unable to walk or bathe himself. He is homebound with daily seizures and in need of a bathroom that is accessible to make his care easier for his family. The scope of this project involved widening the bathroom and adding a roll-in shower providing a safe environment for his care.

Max Project Fundraising Flyer

Rincon Family with Project Team



Project Updates

February 2015

  • Preliminary drawings sent to SLATERPAULL (architect)
  • Sought contractor to remove existing hot tub

March 2015

  • Site visit with US Engineering (mechanical subcontractor) and Delaney's Electric, Inc. (electrical subcontractor)
  • Preliminary Quantity Take-Off's and schedule completed
  • Drawings prepared for permit submittal; permit received
  • Framed floor joists and east wall

April 2015

  • Framing for flooring inspected and approved
  • Secured drywall installer/finisher and started plumbing rough-in
  • Bobcat of the Rockies delivered drywall, tile, and supplies donated by Gypsum Products, Inc., and Capco Tile and Stone
  • Six employees of Swinerton Builders helped with drywall installation on 4/11/2015
  • Hung door, tiled, painted exterior walls
  • Placed the Schluter Ditra underlayment and painted all interior walls
  • Installed tile, MEP fixtures, casework and trim
  • Scheduled final inspections

May 2015

  • Completed punchlist items and obtained Certificate of Occupancy